| 7-05-07 Flooring 1/2 Laid. |
To avoid CREAKING
FLOORS, the floors
are glued and installed with special nails.
The access doors to the crawl space will
be in the MBR (bottom left) & far (top left)
BR closets.
| COMPLETED FLOOR |

|
Flooring completed 7-10-07. Contractor said this is the most plywood he has ever
put on a single floor. Notice the access door in bedroom closet for the crawl space.
| THE WALLS ARE GOING UP |

|
Yeah! Yeah! Yeah! 7-11-07 Should have gone to Vegas with that number.
The walls are finally going up starting with the main one. THE BEDROOM.

|
| GREAT PROGRESS TODAY |
The walls are almost completed, Just a couple more walls to go. This is looking
NE from end to end.

|
| THE FINAL LINK. |
Let the 3 pigs HUFF & PUFF all they want. The house is all tied together and the inside walls are in progress. Roof
Trusses coming soon.

|
| Front of the house |
The front of the house looks South. Look at all that dirt I have to shovel. Looks like I will be busy for
awhile.

Garage (Dam, I forgot Harold's lift) was poured
7/26/07. Had lots of headroom for the lift
at this time.

The forelady helping with the curing. Has to be watered everyday for 7 days. That's
all that was done for that period.
|